Overview
Firm360 supports task-level time estimates and the ability to log time directly to tasks within projects. This allows you to track task progress more accurately and stay on budget.
Important Notes:
- Estimated Total is based on Open or Completed Tasks. Total does not include Task Estimates for Tasks that have not yet triggered.
- Only user with the Admin role and/or Time Tracking Admin can edit Task Level Estimates.
Enable Task-Level Settings
Before using task-level estimates, ensure the following settings are enabled:
-
Use Task-Level Estimates
-
Require Task Selection for Time Entries (optional; enabling this will require users to select a task when logging time for the project)
Note: Enabling “Require Task Selection” is optional. If not enabled, time entries can be logged without selecting a task.
These settings can be enabled in three places:
-
Project Template: Navigate to Customizations → Project Templates → (select template) → Click Blue Edit Pencil to Enable Task Estimates Settings.(Admin User Role Required)
-
Client Level: Navigate to the client → Projects → Under Recurring Projects List → Click Edit to Enable Task Estimates Settings (Recurring Projects User Role Required)
-
Active Project: Open the project → Click Blue Edit Pencil to Enable Task Estimates Settings for this Specific Project
Add or Edit Hour Estimates to a Task
- Navigate to Project Tasks (or Global Tasks / Client Tasks / Project Templates).
- Click Add Task or Edit an existing task.
- Enter the number of Estimated Hours for the task (decimals allowed, e.g., 1.5).
- Examples: 1.5, 3, 10.25
- Maximum: 9999.99
-
Click Save.
All updates are reflected in project main views, task lists, and reports.
Tip: Tasks copied from templates inherit the template’s hour estimates.
Log Time to a Task
- Select Client and Project in your time entry workflow.
- If the project has tasks, a Task dropdown will appear.
- Select the appropriate task.
- Enter hours worked and save (or stop timer if using Start Timer).
Notes:
- Only tasks linked to the selected project appear when tracking time.
- Inactive tasks remain on historical entries but cannot be selected for new time entries.
- If the project requires task selection, leaving the task blank will trigger an error: “A task is required for this project.”
View Task Estimates vs Actuals
Important Note: Estimated Total is based on Open or Completed Tasks. Total does not include Task Estimates for Tasks that have not yet triggered.
- Navigate to the Main Project Tab or Tasks Tab.
- Task-level estimates and logged hours are summed and displayed.
-
Visual indicators show progress vs estimates for each task.
Reporting
- Timesheet: Time Tracking Reports - Timesheets - CSV exports now include task names.
- Time Tracking Tab: Any User can view the Tasks associated with their time entries on the Time Tracking Tab
-
Project Estimate to Actual Report: Pulls task-level or project-level totals depending on project configuration. Projects Reports - Project Estimate To Actual