Status Transition Rules can automatically change a project's status based on certain conditions.

 

Here's how to enter a rule:

  • Navigate to Customizations under Admin on the black ribbon on the left.
  • Locate Status Transition Rules and click on add a project status transition rule

 

 

Complete the form: 

 

mceclip1.png

 

Choose the current project status from the dropdown list. Then select the condition:

1. Days Passed - enter the number of days to pass from the start of the project.

2. All Tasks Completed - all the tasks are completed for this project. 

3. All Client Actions Complete - the client has completed all their actionable items in their portal 

4. Delivery Package Complete - the client has marked the Delivery Package as Complete in their portal

 

 